Skip to main content
Energy Review
Energy data

UK Electricity Interconnectors: Capacity and Pipeline

Great Britain is an island, but its electricity system is not isolated. A set of high-voltage cables under the sea and across the Irish border let it buy power from its neighbours when they are cheaper, and sell to them when they are not.

This page is the official NESO register of the connection contracts behind those links: what is built, what is contracted but not yet built, and how much each can carry in each direction.

What an interconnector actually is

An interconnector is a direct-current cable joining two alternating- current grids, with a converter station at each end. That design is the point rather than an engineering curiosity: two systems run by different operators cannot be wired together directly and stay stable, but converting to DC and back lets them exchange power while each keeps control of its own frequency.

It also means the flow is dispatched rather than emergent. Somebody decides how much to send and which way, usually through a market that settles the price on each side. Power moves toward the more expensive market, which is why the direction can reverse within a day.

The contract register

NESO publishes the contracted connection capability for each link. The figures below are that register, grouped by project status and by the transmission owner whose network the link connects into.

One caution about the status table before you read it: a staged project can appear under more than one status at once, so the counts are not additive. That is a property of how connection contracts are written, not a fault in the data.

Great Britain · NESO contract register

32 active and future interconnector projects

The register records contracted transmission capacity. It does not show how much electricity is flowing right now or promise that every proposed link will be delivered.

Currently contracted into GB

10.8

GW of import capacity

Currently contracted out of GB

11.1

GW of export capacity

Active + future import

39.4

GW across the full register

Active + future export

40

GW across the full register

Built links

11

Additional import contracted

28.7 GW

Contract records retained

33

Read the directions carefully

Import and export use the GB grid's perspective

Import capacitymeans power the interconnector can feed into Great Britain's transmission system.

Export capacity means power the GB system can supply to the interconnector connection site.

Neither figure is live flow. See the live electricity page for metered cross-border power.

Project status

What stage are the links at?

One staged link can appear under more than one status, so the group counts should not be added together.

StatusLinksImportExport
Scoping1723.2 GW23.3 GW
Built1110.8 GW11.1 GW
Awaiting consents34 GW4.1 GW
Under construction / commissioning11.4 GW1.5 GW

Host transmission owner

Where do the links connect?

NGET

28

England & Wales transmission · 35 GW import

SHET

2

North of Scotland transmission · 3.2 GW import

SPT

2

South of Scotland transmission · 1.2 GW import

Contracted timing

Published changes by year

A past effective date can remain in the register until NESO updates the record. It is not evidence that capacity is live.

YearLinksImport changeExport change
2022past10.2 GW0 GW
2024past11.6 GW1.6 GW
202611.4 GW1.5 GW
202711 GW1 GW
202810.8 GW0.8 GW
202934.4 GW4.4 GW
203034.8 GW4.9 GW
203121.9 GW2 GW
203222 GW2 GW
203323.6 GW3.6 GW
203511.8 GW1.8 GW
203611 GW1.1 GW
203734.4 GW4.4 GW

Full register

All 32 links

Directional totals are deduplicated at base project-number level. All 33 underlying contract rows remain in the API.

LinkStatusGB connection siteEffectiveImport totalExport total
Aquind InterconnectorAquind LimitedAwaiting consentsLovedean 400kV Substation31 Dec 20302 GW2.1 GW
Auchencrosh (interconnector CCT)MOYLE INTERCONNECTOR LIMITEDBuiltAuchencrosh 275kV1 Apr 2022 · 1 Aug 20220.5 GW0.5 GW
BritnedBRITNED DEVELOPMENT LIMITEDBuiltGrain 400kV Substation1.2 GW1.2 GW
Celtic MPINational Grid Interconnector Holdings LimitedScopingAlverdiscott 400kV Substation31 Oct 20371.5 GW1.5 GW
Continental LinkNational Grid Interconnector Holdings LimitedScopingBirkhill Wood 400kV Substation31 Oct 20351.8 GW1.8 GW
CronosCRONOS ENERGY LTDScopingKemsley 400kV Substation31 Oct 20291.4 GW1.4 GW
East West InterconnectorEIRGRID INTERCONNECTOR DESIGNATED ACTIVITY COMPANYBuiltDeeside 400kV Substation0.5 GW0.6 GW
ElecLinkELECLINK LIMITEDBuiltSellindge 400kV Substation1 GW1.1 GW
FAB Link InterconnectorFAB Link LimitedAwaiting consentsExeter 400kV Substation30 Sept 20321.3 GW1.3 GW
GB-EU MPIWindgridScopingFiddes 400kV Substation31 Oct 20331.8 GW1.8 GW
GreenlinkGREENLINK INTERCONNECTOR LIMITEDBuiltPembroke 400kV Substation0.5 GW0.5 GW
Gridlink InterconnectorGridlink Interconnector LimitedScopingKingsnorth 400kV Substation31 Mar 20291.5 GW1.5 GW
IFA InterconnectorNATIONAL GRID INTERCONNECTORS LIMITEDBuiltSellindge 400kV Substation2 GW2 GW
IFA2 InterconnectorNATIONAL GRID IFA 2 LIMITEDBuiltChilling 400kV Substation1.1 GW1.2 GW
Isle of Man InterconnectorMANX UTILITIESBuiltBispham 132kV Substation0.1 GW0.1 GW
Kulizumboo InterconnectorKULIZUMBOO LIMITEDScopingCanterbury 400kV GIS Substation1 Apr 20310.7 GW0.7 GW
LionLink (EuroLink)National Grid Interconnector Holdings LimitedScopingFriston 400kV Substation30 Oct 20241.6 GW1.6 GW
LIRIC InterconnectorTI LIRIC LimitedScopingHunterston East 400kV31 Oct 20320.7 GW0.7 GW
Low Carbon LinkLOW CARBON SOLAR PARK 39 LIMITEDScopingSOUTH WALES WEST CONNECTION NODE C 400KV SUBSTATION31 Oct 20371.4 GW1.4 GW
MARESMaresconnect LimitedAwaiting consentsBodelwyddan 400kV Substation30 Nov 20280.8 GW0.8 GW
NautilusNational Grid Interconnector Holdings LimitedScopingWallend 400kV Substation31 Oct 20291.5 GW1.5 GW
Nemo LinkNEMO LINK LIMITEDBuiltRichborough 400kV Substation1 GW1 GW
NeuConnect InterconnectorNeuconnect Britain LtdUnder construction / commissioningGrain West 400kV Substation1 Aug 20261.4 GW1.5 GW
NorthConnectNORTHCONNECT LIMITEDScopingPeterhead 400kV Substation1 Mar 20301.4 GW1.4 GW
NS LinkNATIONAL GRID NORTH SEA LINK LIMITEDBuiltBlyth GSP1.4 GW1.5 GW
Project CobaltGETLINK PROJECTS 2 LIMITEDScopingEast Kent Connection Node B 400kV Substation30 Oct 20361 GW1.1 GW
SENECAFRONTIER POWER INTERNATIONAL LIMITEDScopingMablethorpe 400kV Substation30 Nov 20311.2 GW1.3 GW
TarchonTarchon Energy LimitedScopingEast Anglia Connection Node 400kV Substation31 Oct 20301.4 GW1.4 GW
Teeside MPINational Grid Interconnector Holdings LimitedScopingWearside Connection Node B 400kV Substation31 Oct 20331.8 GW1.8 GW
The SuperconnectionASC ENERGY PLCScopingCreyke Beck 400kV Substation1 Sept 20271 GW1 GW
Viking Link Denmark InterconnectorNATIONAL GRID VIKING LINK LIMITEDBuiltBicker Fen 400kV Substation1.5 GW1.5 GW
Western MPINational Grid Interconnector Holdings LimitedScopingConnah's Quay 400kV Substation31 Oct 20371.5 GW1.5 GW

Limits and provenance

What this register cannot tell you

NESO publishes GB connection-site names, not coordinates or partner countries. We therefore do not guess a destination, draw a route or offer a postcode lookup for this dataset.

Moyle's published 500 MW TEC is subject to operational restrictions. Project status is recorded as far as NESO is aware and should not replace planning or construction records.

Source: National Energy System OperatorInterconnector Register · National Energy SO Open Data Licence v1.0. Supported by National Energy SO Open Data

Import and export are not the same number

The register quotes capability in each direction separately, and the two often differ for the same link.

Both are stated from the Great Britain grid’s point of view. Import capacity is what the link can feed into the GB transmission system; export capacity is what the GB system can supply to the link’s connection site. The asymmetry usually comes from the local network rather than the cable — the substation, the surrounding circuits and what else is connected nearby all constrain how much can be absorbed or supplied at that point.

Neither figure is a flow. Nothing on this page tells you what any link is doing at the moment, only what it is contracted to be able to do. For actual metered flow, that is on the live electricity page.

Why interconnectors matter to your bill

Wholesale electricity in Britain is priced by the most expensive plant needed to meet demand. Usually that is a gas station, so the gas price ends up setting the electricity price for everyone.

An interconnector adds a competitor to that final slot. If power can be bought from a neighbour for less than the marginal gas plant would charge, it displaces the gas plant and the price settles lower — for every unit sold in that period, not only the imported ones. That is the main route by which cross-border capacity reaches a household bill, though it arrives diluted and delayed: on a capped or fixed tariff, wholesale movements take months to show up, if they show up at all. The price cap page sets out how much of a bill is wholesale cost in the first place.

There is a security argument too. More links mean more independent sources of supply on a tight evening, which is worth something even in the hours when the price effect is small.

Contracted is not built

The register includes projects at every stage, from operating links to proposals that have a connection agreement and nothing else.

Subsea cables are among the slowest infrastructure there is: seabed surveys, consents on both sides of a border, cable manufacturing slots booked years ahead, converter stations at each landing point. Projects that hold a contract for years without moving are normal, and some are abandoned. Read the status column before treating anything here as future capacity, and read the grid connection queue alongside it for the same distinction applied to generation.

Is imported electricity clean?

It depends which link, and when. Electrons carry no label, so an import is best understood as a share of whatever the neighbouring system was generating at that moment rather than as output from a particular plant.

That makes the answer specific to each connection. A link to a hydro-dominated system delivers something close to that system’s mix; a link to a nuclear-heavy one, that mix; a link to a system burning coal or gas at the time, that. Great Britain’s published grid carbon intensity does account for imports, which is why the live figures move when a large link changes direction.

It is also why claims that Britain has “offshored its emissions” through interconnectors need checking against the direction of flow. The cables run both ways, and in windy conditions Britain is frequently the exporter.

Frequently asked questions

What is an electricity interconnector?

A high-voltage cable, usually undersea, that links the Great Britain electricity system to a neighbouring one so power can flow in either direction. They are direct current rather than the alternating current used on the grid itself, with converter stations at each end, which is what lets two separately-run systems trade without having to stay in step with each other.

Does the UK import electricity?

Yes, routinely — and it exports too, sometimes on the same day. Power flows toward whichever side is more expensive at that moment, so the direction changes with prices, wind output and demand on both sides. The live electricity page shows what each link is doing now; this page shows the contracted capability that sets the ceiling.

How much electricity can Britain import at once?

The register on this page adds up the contracted import capability across every link, in gigawatts. Treat it as a ceiling rather than a delivery figure: links go offline for maintenance and faults, and a link only imports when the market on the other side is cheaper.

Do interconnectors make electricity cheaper?

Generally yes, by letting Britain buy from a cheaper market instead of running a more expensive plant at home. The effect is not guaranteed in any given hour — if the continent is short and Britain is not, the flow reverses and Britain exports into higher prices. Over a year, more connection usually means lower and less volatile wholesale prices.

Is electricity imported through an interconnector low carbon?

It depends on the link and the hour. A cable to Norway is drawing on a largely hydro system, one to France on a largely nuclear one; others connect to mixed systems. Grid carbon figures for Great Britain account for imports, but any single import is a share of the neighbour’s whole generation mix at that moment rather than a specific power station.

Related reading

Rob Gibbs

Written by

Rob Gibbs

Hi, I'm Rob, and I run Energy-Review.co.uk. I initially started this project in 2018 when I was looking to switch energy suppliers and found there wasn't a website that provided simple, data-backed reviews on all the suppliers available. Since then, I have spent a lot of time (too much, some may say!) looking at all publicly available data about each supplier and writing reviews using this information. These reviews are updated as regularly as possible, and any data is backed up by a source where necessary. I have also started writing guides on various energy-related topics, which hopefully you will find useful. If you find any issues, please use our contact form to let us know.