Skip to main content
Energy Review
Energy data

UK Electricity Interconnectors: Capacity and Pipeline

See operating and proposed electricity links between Great Britain and neighbouring systems, including their import and export capacity.

What an interconnector actually is

An interconnector is a high-voltage cable linking two electricity systems. Power normally flows towards the more expensive market, so a link can reverse direction during the day.

The contract register

The figures are grouped by project status and the transmission network each link connects to.

A project built in stages can appear under more than one status, so do not add the project counts together.

Great Britain · NESO contract register

34 active and future interconnector projects

The register records contracted transmission capacity. It does not show how much electricity is flowing right now or promise that every proposed link will be delivered.

Currently contracted into GB

11.8

GW of import capacity

Currently contracted out of GB

12.1

GW of export capacity

Active + future import

43.8

GW across the full register

Active + future export

44.4

GW across the full register

Built links

11

Additional import contracted

32.1 GW

Contract records retained

36

Read the directions carefully

Import and export use the GB grid's perspective

Import capacity means power the interconnector can feed into Great Britain's transmission system.

Export capacity means power the GB system can supply to the interconnector connection site.

Neither figure is live flow. See the live electricity page for metered cross-border power.

Project status

What stage are the links at?

One staged link can appear under more than one status, so the group counts should not be added together.

StatusLinksImportExport
Scoping1927.6 GW27.7 GW
Built1110.8 GW11.1 GW
Awaiting consents34 GW4.1 GW
Under construction / commissioning11.4 GW1.5 GW

Host transmission owner

Where do the links connect?

NGET

30

England & Wales transmission · 39.4 GW import

SHET

2

North of Scotland transmission · 3.2 GW import

SPT

2

South of Scotland transmission · 1.2 GW import

Contracted timing

Published changes by year

A past effective date can remain in the register until NESO updates the record. It is not evidence that capacity is live.

YearLinksImport changeExport change
2022past10.2 GW0 GW
202711.4 GW1.5 GW
202934.4 GW4.4 GW
203057.4 GW7.4 GW
203121.9 GW2 GW
203256.4 GW6.4 GW
203311.8 GW1.8 GW
203523.6 GW3.6 GW
203611 GW1.1 GW
203745.2 GW5.2 GW
View all 34 links

Import and export capacity are shown separately for each link.

LinkStatusGB connection siteEffectiveImport totalExport total
AlverdiscottXLINKS 1 LTDScopingAlverdiscott 400kV Substation30 Aug 20301.8 GW1.8 GW
Alverdiscott 2XLINKS 1 LTDScopingAlverdiscott 400kV Substation30 Aug 20321.8 GW1.8 GW
Aquind InterconnectorAquind LimitedAwaiting consentsLovedean 400kV Substation30 Jun 20302 GW2.1 GW
Auchencrosh (interconnector CCT)MOYLE INTERCONNECTOR LIMITEDBuiltAuchencrosh 275kV1 Apr 2022 · 1 Aug 20220.5 GW0.5 GW
BritnedBRITNED DEVELOPMENT LIMITEDBuiltGrain 400kV Substation—1.2 GW1.2 GW
Celtic MPINational Grid Interconnector Holdings LimitedScopingAlverdiscott 400kV Substation31 Oct 20371.5 GW1.5 GW
Continental LinkNational Grid Interconnector Holdings LimitedScopingBirkhill Wood 400kV Substation31 Oct 20351.8 GW1.8 GW
CronosCRONOS ENERGY LTDScopingKemsley 400kV Substation31 Oct 20291.4 GW1.4 GW
East West InterconnectorEIRGRID INTERCONNECTOR DESIGNATED ACTIVITY COMPANYBuiltDeeside 400kV Substation—0.5 GW0.6 GW
ElecLinkELECLINK LIMITEDBuiltSellindge 400kV Substation—1 GW1.1 GW
FAB Link InterconnectorFAB Link LimitedAwaiting consentsExeter 400kV Substation30 Sept 20321.3 GW1.3 GW
GB-EU MPIWindgridScopingFiddes 400kV Substation31 Oct 20331.8 GW1.8 GW
GreenlinkGREENLINK INTERCONNECTOR LIMITEDBuiltPembroke 400kV Substation—0.5 GW0.5 GW
Gridlink InterconnectorGridlink Interconnector LimitedScopingKingsnorth 400kV Substation31 Mar 20291.5 GW1.5 GW
IFA InterconnectorNATIONAL GRID INTERCONNECTORS LIMITEDBuiltSellindge 400kV Substation—2 GW2 GW
IFA2 InterconnectorNATIONAL GRID IFA 2 LIMITEDBuiltChilling 400kV Substation—1.1 GW1.2 GW
Isle of Man InterconnectorMANX UTILITIESBuiltBispham 132kV Substation—0.1 GW0.1 GW
Kulizumboo InterconnectorKULIZUMBOO LIMITEDScopingCanterbury 400kV GIS Substation1 Apr 20310.7 GW0.7 GW
LionLink (EuroLink)National Grid Interconnector Holdings LimitedScopingFriston 400kV Substation31 Oct 20321.6 GW1.6 GW
LIRIC InterconnectorTI LIRIC LimitedScopingHunterston East 400kV31 Oct 20320.7 GW0.7 GW
Low Carbon LinkLOW CARBON SOLAR PARK 39 LIMITEDScopingSOUTH WALES WEST CONNECTION NODE C 400KV SUBSTATION31 Oct 20371.4 GW1.4 GW
MARESMaresconnect LimitedAwaiting consentsBodelwyddan 400kV Substation30 Jun 20300.8 GW0.8 GW
NautilusNational Grid Interconnector Holdings LimitedScopingWallend 400kV Substation31 Oct 20291.5 GW1.5 GW
Nemo LinkNEMO LINK LIMITEDBuiltRichborough 400kV Substation—1 GW1 GW
NeuConnect InterconnectorNeuconnect Britain LtdUnder construction / commissioningWallend 400kV Substation7 Jul 20271.4 GW1.5 GW
NorthConnectNORTHCONNECT LIMITEDScopingPeterhead 400kV Substation1 Mar 20301.4 GW1.4 GW
NS LinkNATIONAL GRID NORTH SEA LINK LIMITEDBuiltBlyth GSP—1.4 GW1.5 GW
Project CobaltGETLINK PROJECTS 2 LIMITEDScopingEast Kent Connection Node B 400kV Substation30 Oct 20361 GW1.1 GW
SENECAFRONTIER POWER INTERNATIONAL LIMITEDScopingMablethorpe 400kV Substation30 Nov 20311.2 GW1.3 GW
TarchonTarchon Energy LimitedScopingEast Anglia Connection Node 400kV Substation31 Oct 20301.4 GW1.4 GW
Teeside MPINational Grid Interconnector Holdings LimitedScopingWearside Connection Node B 400kV Substation30 Oct 20351.8 GW1.8 GW
The SuperconnectionASC ENERGY PLCScopingBirkhill Wood 400kV Substation28 Oct 2032 · 28 Oct 20371.8 GW1.8 GW
Viking Link Denmark InterconnectorNATIONAL GRID VIKING LINK LIMITEDBuiltBicker Fen 400kV Substation—1.5 GW1.5 GW
Western MPINational Grid Interconnector Holdings LimitedScopingConnah's Quay 400kV Substation31 Oct 20371.5 GW1.5 GW

Limits

What this register cannot tell you

NESO publishes GB connection-site names, not coordinates or partner countries. We therefore do not guess a destination, draw a route or offer a postcode lookup for this dataset.

Published capacity can be subject to operational restrictions. Project status is recorded as far as NESO is aware and should not replace planning or construction records.

Import and export are not the same number

Import capacity is what a link can feed into Great Britain; export capacity is what Great Britain can send through it. The two can differ because the surrounding networks have different limits.

These are capacity limits, not current flows. See the live electricity page.

Why interconnectors matter to your bill

Interconnectors let Britain buy from a cheaper neighbouring market instead of running a more expensive plant at home. This can reduce wholesale prices and add another source of supply during tight periods. The price cap page sets out how wholesale costs affect a household bill.

Contracted is not built

A contract does not mean a link will be built. Check the status before treating proposed capacity as available, and see the grid connection queue for the same distinction across generation projects.

Is imported electricity clean?

It depends on the neighbouring system’s generation at that hour. Great Britain’s grid carbon-intensity figures include imports, so the live figures move when a large link changes direction.

Frequently asked questions

What is an electricity interconnector?

A high-voltage cable, usually undersea, that links the Great Britain electricity system to a neighbouring one so power can flow in either direction. They are direct current rather than the alternating current used on the grid itself, with converter stations at each end, which is what lets two separately-run systems trade without having to stay in step with each other.

Does the UK import electricity?

Yes, routinely — and it exports too, sometimes on the same day. Power flows toward whichever side is more expensive at that moment, so the direction changes with prices, wind output and demand on both sides. The live electricity page shows what each link is doing now; this page shows the contracted capability that sets the ceiling.

How much electricity can Britain import at once?

The register on this page adds up the contracted import capability across every link, in gigawatts. Treat it as a ceiling rather than a delivery figure: links go offline for maintenance and faults, and a link only imports when the market on the other side is cheaper.

Do interconnectors make electricity cheaper?

Generally yes, by letting Britain buy from a cheaper market instead of running a more expensive plant at home. The effect is not guaranteed in any given hour — if the continent is short and Britain is not, the flow reverses and Britain exports into higher prices. Over a year, more connection usually means lower and less volatile wholesale prices.

Is electricity imported through an interconnector low carbon?

It depends on the link and the hour. A cable to Norway is drawing on a largely hydro system, one to France on a largely nuclear one; others connect to mixed systems. Grid carbon figures for Great Britain account for imports, but any single import is a share of the neighbour’s whole generation mix at that moment rather than a specific power station.

Related reading

Rob Gibbs

Written by

Rob Gibbs

Hi, I'm Rob, and I run Energy-Review.co.uk. I initially started this project in 2018 when I was looking to switch energy suppliers and found there wasn't a website that provided simple, data-backed reviews on all the suppliers available. Since then, I have spent a lot of time (too much, some may say!) looking at all publicly available data about each supplier and writing reviews using this information. These reviews are updated as regularly as possible, and any data is backed up by a source where necessary. I have also started writing guides on various energy-related topics, which hopefully you will find useful. If you find any issues, please use our contact form to let us know.