UK Electricity Interconnectors: Capacity and Pipeline
Great Britain is an island, but its electricity system is not isolated. A set of high-voltage cables under the sea and across the Irish border let it buy power from its neighbours when they are cheaper, and sell to them when they are not.
This page is the official NESO register of the connection contracts behind those links: what is built, what is contracted but not yet built, and how much each can carry in each direction.
What an interconnector actually is
An interconnector is a direct-current cable joining two alternating- current grids, with a converter station at each end. That design is the point rather than an engineering curiosity: two systems run by different operators cannot be wired together directly and stay stable, but converting to DC and back lets them exchange power while each keeps control of its own frequency.
It also means the flow is dispatched rather than emergent. Somebody decides how much to send and which way, usually through a market that settles the price on each side. Power moves toward the more expensive market, which is why the direction can reverse within a day.
The contract register
NESO publishes the contracted connection capability for each link. The figures below are that register, grouped by project status and by the transmission owner whose network the link connects into.
One caution about the status table before you read it: a staged project can appear under more than one status at once, so the counts are not additive. That is a property of how connection contracts are written, not a fault in the data.
Great Britain · NESO contract register
32 active and future interconnector projects
The register records contracted transmission capacity. It does not show how much electricity is flowing right now or promise that every proposed link will be delivered.
Currently contracted into GB
10.8
GW of import capacity
Currently contracted out of GB
11.1
GW of export capacity
Active + future import
39.4
GW across the full register
Active + future export
40
GW across the full register
Built links
11
Additional import contracted
28.7 GW
Contract records retained
33
Read the directions carefully
Import and export use the GB grid's perspective
Import capacitymeans power the interconnector can feed into Great Britain's transmission system.
Export capacity means power the GB system can supply to the interconnector connection site.
Neither figure is live flow. See the live electricity page for metered cross-border power.
Project status
What stage are the links at?
One staged link can appear under more than one status, so the group counts should not be added together.
| Status | Links | Import | Export |
|---|---|---|---|
| Scoping | 17 | 23.2 GW | 23.3 GW |
| Built | 11 | 10.8 GW | 11.1 GW |
| Awaiting consents | 3 | 4 GW | 4.1 GW |
| Under construction / commissioning | 1 | 1.4 GW | 1.5 GW |
Host transmission owner
Where do the links connect?
NGET
28
England & Wales transmission · 35 GW import
SHET
2
North of Scotland transmission · 3.2 GW import
SPT
2
South of Scotland transmission · 1.2 GW import
Contracted timing
Published changes by year
A past effective date can remain in the register until NESO updates the record. It is not evidence that capacity is live.
| Year | Links | Import change | Export change |
|---|---|---|---|
| 2022past | 1 | 0.2 GW | 0 GW |
| 2024past | 1 | 1.6 GW | 1.6 GW |
| 2026 | 1 | 1.4 GW | 1.5 GW |
| 2027 | 1 | 1 GW | 1 GW |
| 2028 | 1 | 0.8 GW | 0.8 GW |
| 2029 | 3 | 4.4 GW | 4.4 GW |
| 2030 | 3 | 4.8 GW | 4.9 GW |
| 2031 | 2 | 1.9 GW | 2 GW |
| 2032 | 2 | 2 GW | 2 GW |
| 2033 | 2 | 3.6 GW | 3.6 GW |
| 2035 | 1 | 1.8 GW | 1.8 GW |
| 2036 | 1 | 1 GW | 1.1 GW |
| 2037 | 3 | 4.4 GW | 4.4 GW |
Full register
All 32 links
Directional totals are deduplicated at base project-number level. All 33 underlying contract rows remain in the API.
| Link | Status | GB connection site | Effective | Import total | Export total |
|---|---|---|---|---|---|
| Aquind InterconnectorAquind Limited | Awaiting consents | Lovedean 400kV Substation | 31 Dec 2030 | 2 GW | 2.1 GW |
| Auchencrosh (interconnector CCT)MOYLE INTERCONNECTOR LIMITED | Built | Auchencrosh 275kV | 1 Apr 2022 · 1 Aug 2022 | 0.5 GW | 0.5 GW |
| BritnedBRITNED DEVELOPMENT LIMITED | Built | Grain 400kV Substation | — | 1.2 GW | 1.2 GW |
| Celtic MPINational Grid Interconnector Holdings Limited | Scoping | Alverdiscott 400kV Substation | 31 Oct 2037 | 1.5 GW | 1.5 GW |
| Continental LinkNational Grid Interconnector Holdings Limited | Scoping | Birkhill Wood 400kV Substation | 31 Oct 2035 | 1.8 GW | 1.8 GW |
| CronosCRONOS ENERGY LTD | Scoping | Kemsley 400kV Substation | 31 Oct 2029 | 1.4 GW | 1.4 GW |
| East West InterconnectorEIRGRID INTERCONNECTOR DESIGNATED ACTIVITY COMPANY | Built | Deeside 400kV Substation | — | 0.5 GW | 0.6 GW |
| ElecLinkELECLINK LIMITED | Built | Sellindge 400kV Substation | — | 1 GW | 1.1 GW |
| FAB Link InterconnectorFAB Link Limited | Awaiting consents | Exeter 400kV Substation | 30 Sept 2032 | 1.3 GW | 1.3 GW |
| GB-EU MPIWindgrid | Scoping | Fiddes 400kV Substation | 31 Oct 2033 | 1.8 GW | 1.8 GW |
| GreenlinkGREENLINK INTERCONNECTOR LIMITED | Built | Pembroke 400kV Substation | — | 0.5 GW | 0.5 GW |
| Gridlink InterconnectorGridlink Interconnector Limited | Scoping | Kingsnorth 400kV Substation | 31 Mar 2029 | 1.5 GW | 1.5 GW |
| IFA InterconnectorNATIONAL GRID INTERCONNECTORS LIMITED | Built | Sellindge 400kV Substation | — | 2 GW | 2 GW |
| IFA2 InterconnectorNATIONAL GRID IFA 2 LIMITED | Built | Chilling 400kV Substation | — | 1.1 GW | 1.2 GW |
| Isle of Man InterconnectorMANX UTILITIES | Built | Bispham 132kV Substation | — | 0.1 GW | 0.1 GW |
| Kulizumboo InterconnectorKULIZUMBOO LIMITED | Scoping | Canterbury 400kV GIS Substation | 1 Apr 2031 | 0.7 GW | 0.7 GW |
| LionLink (EuroLink)National Grid Interconnector Holdings Limited | Scoping | Friston 400kV Substation | 30 Oct 2024 | 1.6 GW | 1.6 GW |
| LIRIC InterconnectorTI LIRIC Limited | Scoping | Hunterston East 400kV | 31 Oct 2032 | 0.7 GW | 0.7 GW |
| Low Carbon LinkLOW CARBON SOLAR PARK 39 LIMITED | Scoping | SOUTH WALES WEST CONNECTION NODE C 400KV SUBSTATION | 31 Oct 2037 | 1.4 GW | 1.4 GW |
| MARESMaresconnect Limited | Awaiting consents | Bodelwyddan 400kV Substation | 30 Nov 2028 | 0.8 GW | 0.8 GW |
| NautilusNational Grid Interconnector Holdings Limited | Scoping | Wallend 400kV Substation | 31 Oct 2029 | 1.5 GW | 1.5 GW |
| Nemo LinkNEMO LINK LIMITED | Built | Richborough 400kV Substation | — | 1 GW | 1 GW |
| NeuConnect InterconnectorNeuconnect Britain Ltd | Under construction / commissioning | Grain West 400kV Substation | 1 Aug 2026 | 1.4 GW | 1.5 GW |
| NorthConnectNORTHCONNECT LIMITED | Scoping | Peterhead 400kV Substation | 1 Mar 2030 | 1.4 GW | 1.4 GW |
| NS LinkNATIONAL GRID NORTH SEA LINK LIMITED | Built | Blyth GSP | — | 1.4 GW | 1.5 GW |
| Project CobaltGETLINK PROJECTS 2 LIMITED | Scoping | East Kent Connection Node B 400kV Substation | 30 Oct 2036 | 1 GW | 1.1 GW |
| SENECAFRONTIER POWER INTERNATIONAL LIMITED | Scoping | Mablethorpe 400kV Substation | 30 Nov 2031 | 1.2 GW | 1.3 GW |
| TarchonTarchon Energy Limited | Scoping | East Anglia Connection Node 400kV Substation | 31 Oct 2030 | 1.4 GW | 1.4 GW |
| Teeside MPINational Grid Interconnector Holdings Limited | Scoping | Wearside Connection Node B 400kV Substation | 31 Oct 2033 | 1.8 GW | 1.8 GW |
| The SuperconnectionASC ENERGY PLC | Scoping | Creyke Beck 400kV Substation | 1 Sept 2027 | 1 GW | 1 GW |
| Viking Link Denmark InterconnectorNATIONAL GRID VIKING LINK LIMITED | Built | Bicker Fen 400kV Substation | — | 1.5 GW | 1.5 GW |
| Western MPINational Grid Interconnector Holdings Limited | Scoping | Connah's Quay 400kV Substation | 31 Oct 2037 | 1.5 GW | 1.5 GW |
Limits and provenance
What this register cannot tell you
NESO publishes GB connection-site names, not coordinates or partner countries. We therefore do not guess a destination, draw a route or offer a postcode lookup for this dataset.
Moyle's published 500 MW TEC is subject to operational restrictions. Project status is recorded as far as NESO is aware and should not replace planning or construction records.
Source: National Energy System Operator — Interconnector Register · National Energy SO Open Data Licence v1.0. Supported by National Energy SO Open Data
Import and export are not the same number
The register quotes capability in each direction separately, and the two often differ for the same link.
Both are stated from the Great Britain grid’s point of view. Import capacity is what the link can feed into the GB transmission system; export capacity is what the GB system can supply to the link’s connection site. The asymmetry usually comes from the local network rather than the cable — the substation, the surrounding circuits and what else is connected nearby all constrain how much can be absorbed or supplied at that point.
Neither figure is a flow. Nothing on this page tells you what any link is doing at the moment, only what it is contracted to be able to do. For actual metered flow, that is on the live electricity page.
Why interconnectors matter to your bill
Wholesale electricity in Britain is priced by the most expensive plant needed to meet demand. Usually that is a gas station, so the gas price ends up setting the electricity price for everyone.
An interconnector adds a competitor to that final slot. If power can be bought from a neighbour for less than the marginal gas plant would charge, it displaces the gas plant and the price settles lower — for every unit sold in that period, not only the imported ones. That is the main route by which cross-border capacity reaches a household bill, though it arrives diluted and delayed: on a capped or fixed tariff, wholesale movements take months to show up, if they show up at all. The price cap page sets out how much of a bill is wholesale cost in the first place.
There is a security argument too. More links mean more independent sources of supply on a tight evening, which is worth something even in the hours when the price effect is small.
Contracted is not built
The register includes projects at every stage, from operating links to proposals that have a connection agreement and nothing else.
Subsea cables are among the slowest infrastructure there is: seabed surveys, consents on both sides of a border, cable manufacturing slots booked years ahead, converter stations at each landing point. Projects that hold a contract for years without moving are normal, and some are abandoned. Read the status column before treating anything here as future capacity, and read the grid connection queue alongside it for the same distinction applied to generation.
Is imported electricity clean?
It depends which link, and when. Electrons carry no label, so an import is best understood as a share of whatever the neighbouring system was generating at that moment rather than as output from a particular plant.
That makes the answer specific to each connection. A link to a hydro-dominated system delivers something close to that system’s mix; a link to a nuclear-heavy one, that mix; a link to a system burning coal or gas at the time, that. Great Britain’s published grid carbon intensity does account for imports, which is why the live figures move when a large link changes direction.
It is also why claims that Britain has “offshored its emissions” through interconnectors need checking against the direction of flow. The cables run both ways, and in windy conditions Britain is frequently the exporter.
Frequently asked questions
What is an electricity interconnector?
A high-voltage cable, usually undersea, that links the Great Britain electricity system to a neighbouring one so power can flow in either direction. They are direct current rather than the alternating current used on the grid itself, with converter stations at each end, which is what lets two separately-run systems trade without having to stay in step with each other.
Does the UK import electricity?
Yes, routinely — and it exports too, sometimes on the same day. Power flows toward whichever side is more expensive at that moment, so the direction changes with prices, wind output and demand on both sides. The live electricity page shows what each link is doing now; this page shows the contracted capability that sets the ceiling.
How much electricity can Britain import at once?
The register on this page adds up the contracted import capability across every link, in gigawatts. Treat it as a ceiling rather than a delivery figure: links go offline for maintenance and faults, and a link only imports when the market on the other side is cheaper.
Do interconnectors make electricity cheaper?
Generally yes, by letting Britain buy from a cheaper market instead of running a more expensive plant at home. The effect is not guaranteed in any given hour — if the continent is short and Britain is not, the flow reverses and Britain exports into higher prices. Over a year, more connection usually means lower and less volatile wholesale prices.
Is electricity imported through an interconnector low carbon?
It depends on the link and the hour. A cable to Norway is drawing on a largely hydro system, one to France on a largely nuclear one; others connect to mixed systems. Grid carbon figures for Great Britain account for imports, but any single import is a share of the neighbour’s whole generation mix at that moment rather than a specific power station.
Related reading

Written by
Rob Gibbs
Hi, I'm Rob, and I run Energy-Review.co.uk. I initially started this project in 2018 when I was looking to switch energy suppliers and found there wasn't a website that provided simple, data-backed reviews on all the suppliers available. Since then, I have spent a lot of time (too much, some may say!) looking at all publicly available data about each supplier and writing reviews using this information. These reviews are updated as regularly as possible, and any data is backed up by a source where necessary. I have also started writing guides on various energy-related topics, which hopefully you will find useful. If you find any issues, please use our contact form to let us know.
