Skip to main content
Energy Review
Energy data

UK Electricity Grid Connection Queue

Before a wind farm, a battery or a power station can put a single unit onto the grid, it needs somewhere to put it. That is a connection contract, and getting one has become the hardest step in building anything on the British electricity system.

This page is the official NESO register of those contracts: what is queued, how big, what technology, and what date the network has given it.

What a connection contract actually is

Transmission Entry Capacity is the amount of power a project is contracted to be able to export onto the transmission network, measured in megawatts. Without it a project has no right to put electricity anywhere, however complete it is.

It is worth being precise about what it is not. TEC is not planning permission, which is a separate process run by a different body — that pipeline is on our renewable projects page. It is not finance, and it is not a commitment to build. It is a network right, and it can be held for years by a project that has done nothing else at all.

What is in the queue

The register below groups the contracts by technology, status and connection date, with the capacity held by each.

Great Britain · NESO contract register

2,070 projects hold transmission-capacity contracts

These are live contract records, not a prediction that every project will be built. Project-level capacity below is deduplicated using NESO's case-sensitive Project ID.

Cumulative contracted

691.3

GW after project-ID deduplication

Recorded as connected

81.8

GW in the current register fields

Recorded capacity change

609.6

GW contracted above connected capacity

Contract records retained

2,214

Including 266 staged rows

Gate 1 projects

710

Gate 2 projects

67

Gate not yet published

1,293

Project status

Where contract records sit

A staged project can appear in more than one status, so project counts are not additive.

StatusProjectsRecords
Scoping1,4401,501
Built373374
Consents approved153171
Awaiting consents133150
Under construction / commissioning1418

Host transmission owner

Which network hosts the contracts?

NGET

1,195

England & Wales transmission · 1,290 records

SPT

443

South of Scotland transmission · 464 records

SHET

417

North of Scotland transmission · 445 records

OFTO

15

Offshore transmission · 15 records

Gate field

Why are so many Gate values blank?

NESO populates Gate only after a Gate 1 or Gate 2 agreement is countersigned. A blank value is not a planning decision or a prediction about delivery.

Technology mentions

What is seeking grid capacity

Multi-technology contracts count once under every published component. Capacity cannot safely be allocated between them.

TechnologyProjectsRecords
Energy storage1,3961,493
Solar photovoltaics569613
Onshore wind487515
Offshore wind131151
Demand105116
Gas CCGT6568
Reactive compensation6070
Hydro3133
Nuclear2729
Gas OCGT2023
Pumped-storage hydro1721
Combined heat and power1313
Gas reciprocating1113
Biomass1011
Thermal99
Hydrogen45
Energy from waste44
Tidal312
Interconnector33
Oil / advanced gas turbine33
Coal11
Liquid-air energy storage11
Substation11

Contracted timing

Published capacity changes by year

Past dates can remain until NESO marks a project built and connected. These totals inherit the source's aggregation warning.

YearProjectsPublished change
2020past10.4 GW
2022past20.1 GW
2023past60.3 GW
2024past181.5 GW
2025past455.2 GW
20267115.1 GW
202711519.2 GW
202816334.9 GW
202915943.6 GW
203012537.5 GW
203116651.5 GW
20329732.6 GW
203321085.1 GW
203417273.7 GW
203510862.8 GW
20367632.2 GW
203726392.5 GW
20383016.4 GW
2039195.1 GW

Largest recorded changes

The 20 biggest non-built project positions

ProjectTechnologyStatusEffectiveChange
Bute Hydrogen Project 1HALDANE ENERGY PROJECT 1 LIMITEDGas CCGTScoping2035-10-314,800 MW
Drax BECCSDrax Power LimitedBiomass + DemandScoping2035-10-303,906 MW
Bute Hydrogen Project 2HALDANE ENERGY PROJECT 2 LIMITEDGas CCGTScoping2035-10-313,600 MW
Bute Hydrogen Project 3HALDANE ENERGY PROJECT 3 LIMITEDGas CCGTScoping2035-10-313,600 MW
Bute Hydrogen Project 5HALDANE ENERGY PROJECT 5 LIMITEDGas CCGTScoping2035-10-313,600 MW
Bute Hydrogen Project 6Haldane Energy Project 6 LimitedGas CCGTScoping2037-10-313,600 MW
Hinkley Point CNNB GENERATION COMPANY (HPC) LIMITEDNuclearScoping2029-03-313,340 MW
Sizewell CSizewell C LimitedNuclearConsents approved2035-07-313,340 MW
Hornsea Power Station 3HORNSEA PROJECT THREE (UK) LIMITEDEnergy storage + Offshore windConsents approved2026-10-013,000 MW
Marram Wind Offshore Wind FarmMarramwind LimitedOffshore windScoping2031-10-313,000 MW
Hornsea Power Station 4ORSTED HORNSEA PROJECT FOUR LIMITEDOffshore windScoping2028-10-302,600 MW
PortwindSE PORTWIND LTDEnergy storage + Solar photovoltaics + Offshore windScoping2036-12-062,500 MW
Eggborough CCGT - OCGT - BESSEGGBOROUGH POWER LIMITEDEnergy storage + Gas CCGT + Gas OCGTAwaiting consents2026-10-012,450 MW
Bute Hydrogen Project 4HALDANE ENERGY PROJECT 4 LIMITEDGas CCGTScoping2035-10-312,400 MW
Bute Hydrogen Project 7.1HALDANE ENERGY PROJECT 7 LIMITEDEnergy storageScoping2038-10-312,400 MW
OWPL WindfarmOFFSHORE WIND POWER LIMITEDOffshore windScoping2029-12-312,250 MW
East Claydon Green Energy CentreEAST CLAYDON GREEN NG LIMITEDDemand + Energy storage + Solar photovoltaicsAwaiting consents2034-10-012,050 MW
Caledonia Offshore Wind FarmCALEDONIA OFFSHORE WIND FARM LIMITEDOffshore windScoping2031-03-312,000 MW
GallosCorio Generation LimitedOffshore windScoping2036-12-062,000 MW
Machair Offshore Wind FarmSCOTTISHPOWER RENEWABLES (UK) LIMITEDOffshore windScoping2033-09-162,000 MW

Official source and licence

National Energy System Operator Transmission Entry Capacity (TEC) register · Great Britain projects holding Transmission Entry Capacity contracts

Supported by National Energy SO Open Data. The register updates twice weekly; this snapshot was modified 2026-07-31.

Read the queue numbers carefully

A contract is not a forecast. Projects can change, be delayed or never generate. Capacity is not expected output.

Status is indicative. NESO says it is recorded on an “as far as we are aware” basis and is not authoritative planning data.

Duplicates are meaningful. Stages and technologies can carry aggregate capacity, so the API preserves every contract row.

Connection-site names are not geographic coordinates. This page therefore does not offer a postcode lookup or claim a local-area match.

The queue is not a build forecast

Read the total queued capacity as a ceiling, never as a projection.

The queue contains projects that will not be financed, will not get planning permission, or were speculative from the start — an application costs a great deal less than a wind farm, and holding a place in line has had option value even for developers with no firm intention of building. The result is a total that has run far above anything Great Britain could actually use, which tells you plainly that much of it is not real.

What the queue does describe accurately is intent and location: where developers want to build, at what scale, and in what technology. That is genuinely useful, and it is a leading indicator of where the network will be under pressure next. It is simply not a delivery schedule.

Why the wait got so long

The queue lengthened for reasons that were sensible individually and unfortunate together.

It was ordered by application date. A project ready to start construction sat behind older applications that were not ready and might never be, because the rule was first come, first served and readiness did not enter into it. Meanwhile each connection depended on network reinforcement — new lines, new substations — that takes the better part of a decade to consent and build, so the network side could not simply absorb the demand.

Add a surge in applications as renewables became cheap, and the wait moved from months to years. Reform has been aimed squarely at the ordering problem: sorting the queue by whether a project is actually ready to proceed, so that the ones that can be built are not held up by the ones that cannot.

How to read a connection date

The date against a contract is when the network expects to be able to accept that connection. It is not when the project will be finished, and it is emphatically not a promise that it will be started.

Dates also move, usually outward, as reinforcement schemes are re-planned. A date years into the future on a project that has not begun construction is best read as an upper bound on optimism rather than a milestone. Where a date is missing from the register, the page shows it as unknown rather than guessing.

Why this queue matters to bill payers

A queue for a network connection sounds like an industry problem. It reaches households through two routes.

The first is price. Generation that cannot connect cannot compete, and a market with less generation competing to meet demand settles higher. Cheap wind stuck behind a connection date is cheap wind that is not pushing gas out of the price-setting position described on our gas system page.

The second is the cost of the mismatch itself. When generation connects in places the network cannot move power away from, the system operator pays to constrain it off — and that bill is on our grid balancing costs page. The queue is where you can see that problem forming several years before it appears as a cost.

Frequently asked questions

What is the grid connection queue?

The set of electricity projects holding a contract for capacity on the Great Britain transmission network. A generator, battery or interconnector cannot export power without one, so the queue is the pipeline of everything with a formal place in line — built, under construction and merely proposed alike.

What is Transmission Entry Capacity?

TEC is the amount of power a project is contracted to be able to put onto the transmission network, in megawatts. It is a network right rather than a planning permission or a promise to build: a project can hold TEC for years without a single turbine going up.

Does everything in the queue get built?

No, and this is the central caveat. The queue includes projects that will never be financed, never win planning permission, or were only ever placeholders. Total queued capacity is a ceiling on what could connect, not a forecast of what will, and it exceeds what Great Britain could sensibly use several times over.

Why do projects wait years to connect to the grid?

Historically the queue was ordered by application date, so a project that was ready to build sat behind ones that were not, and the network reinforcement each connection depended on took years to design and construct. Reform has been aimed at ordering the queue by readiness instead, so that projects able to proceed are not held up by those that cannot.

Is a connection date a completion date?

No. It is the date the network expects to be able to accept the connection, which is a different thing from when the project will be finished — or whether it will start. Read it as the earliest the network side could be ready, not as a delivery date.

Related reading

Rob Gibbs

Written by

Rob Gibbs

Hi, I'm Rob, and I run Energy-Review.co.uk. I initially started this project in 2018 when I was looking to switch energy suppliers and found there wasn't a website that provided simple, data-backed reviews on all the suppliers available. Since then, I have spent a lot of time (too much, some may say!) looking at all publicly available data about each supplier and writing reviews using this information. These reviews are updated as regularly as possible, and any data is backed up by a source where necessary. I have also started writing guides on various energy-related topics, which hopefully you will find useful. If you find any issues, please use our contact form to let us know.